April 2025

  • No formal works have commenced on site to implement the permission
  • Planting up of the Western POS (Public Open Space phase 1) has begun
  • Archaeological investigation continues
  • Farm animals and equipment have been cleared
  • Fencing (perimeter and other) has been erected

March 2025

  • There are conditions required to be discharged prior to works commencing on site
  • Though tree and hedgerow removal has taken place prior to bird nesting season, the build has not commenced as removal of vegetation does not constitute development
  • The tree and hedgerow removal:
    • was approved through the outline planning permission (20/10997)
    • significant new hedgerow and tree planting will be provided to mitigate this loss